I-75 at County Road 54 (interchange reconstruction and resurfacing)
Project Description
Financial Project Numbers: 421831-4
Project Limits: from south of SR 56 to north of CR 54
Project Length: 4.3 miles
Estimated Construction Cost: $33 million
Contractor: The Lane Construction Corporation
Start Date: February 2, 2009
Estimated Completion Date: August 2010
About this Project
The Florida Department of Transportation's (FDOT) contractor is improving the interchange at Interstate 75 and County Road 54 (CR 54) to accommodate the future widening of CR 54 by Pasco County and to prepare for the future widening of I-75 to six lanes.
The project includes the complete removal and replacement of the existing bridges at CR 54, the resurfacing of I-75 from south of State Road 56 (SR 56) to north of CR 54, and the widening of entrance and exit ramps at CR 54. It also will include the construction of retention ponds, mitigation areas and storm drainage.
Project Detours
Detours will be necessary when overhead bridge work spans the width of eastbound or westbound lanes on CR 54. This work may include bridge demolition, placement of bridge beams, and concrete deck pours. The detours will be in place during overhead bridge operations at night during off-peak hours.
Improvement Highlights
Traffic Flow
There should be minimal impact to local motorists. The construction phasing is designed so that all existing lanes of traffic will be maintained on I-75 and CR 54 during peak traffic hours.
Night Work
In order to maintain the construction schedule and to minimize the impact to the public, it is necessary to perform a considerable amount of work at night. The majority of this work will include asphalt paving and bridge construction operations. Lane closures will be necessary during different phases of the project.
Lane Closure Hours
Interstate 75: 8 p.m. to 5 a.m.
County Road 54: 10 p.m. to 5 a.m.
Interactive Maps
Zoomify Aerials
Click on one of the four maps below; a new window will open and the Zoomifyer software will allow you to click on the map to zoom in closer with each click of the mouse.
Please note: These aerials show additional traffic lanes that will be built in a future project.
South Project Limits | Middle of Project Limits |
North Project Limits | Interchange Detail |
Contact Person(s)
Public & Media Contact
John McShaffrey, APR
Interstate Construction Office
(813) 233-3837
E-mail
Log in to see if you are subscribed to receive updates on this project.
"
Latest Project Updates
CR 54 to be closed under I-75 two nights
Posted 9/3/2010
Lane closures Wednesday night on I-75 from rest areas to north of CR 54
Posted 9/3/2010
View all news for this project
Recent Project Photos
Interactive Maps
Fact Sheets
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Ramp switch for I-275 Exit 39B Tonight!
Posted 9/7/2010
Day and night lane closures on Selmon Expressway
Posted 9/3/2010
Lane closures Wednesday night on I-75 from rest areas to north of CR 54
Posted 9/3/2010