I-75 from County Road 54 to Pasco/Hernando counties line (resurfacing)

Project Description

Financial Project Number: 421504 (from CR 54 to SR 52) & 421505 (from SR 52 to Hernando County line)
Project Limits: from north of CR 54 to Pasco/Hernando counties line
Project Length: 14.4 miles
Estimated Construction Cost: $3.2 million
Contractor: D.A.B. Constructors, Inc.
Start Date: March 7, 2010
Estimated Completion Date: Fall 2010

About this Project
The Florida Department of Transportation's contractor will be milling and resurfacing both directions of I-75 from CR 54 to the Pasco-Hernando County line. The entrance and exit ramps at State Road 52 and County Road 41 will also be milled and resurfaced.

Improvement Highlights

  • Fix the deteriorating condition of the existing roadway for a smoother and better riding surface.Traffic Flow
    The construction phasing is designed so that all existing I-75 traffic lanes will be open during peak hours. There will be detours when the contractor is working on the ramps.

    Night Work
    In order to maintain the construction schedule and to minimize the impact to the public, it is necessary for the contractor to also work at night. Lane closures, traffic shifts, and traffic paces will be used during different phases of the project.

    Lane Closure Hours
    9 p.m. to 6 a.m.