I-75 from Pasco County line to Lockhart Road (resurfacing)

Project Description

Financial Project Number: 422443
Project Limits: from Pasco/Hernando counties line to south of Lockhart Road
Project Length: 3.8 miles
Estimated Construction Cost: $5 million
Contractor: D.A.B. Constructors, Inc.
Start Date: March 7, 2010
Estimated Completion Date: Fall 2010

About this Project
The Florida Department of Transportation's contractor will be milling and resurfacing I-75 from the Pasco-Hernando counties line to south of Lockhart Road in Hernando County.

Improvement Highlights

  • Fix the deteriorating condition of the existing roadway for a smoother and better riding surface.
  • Construct a bridge pier protection system at the Church Road overpass.
  • Replace guardrail where needed.Traffic Flow
    The construction phasing is designed so that all existing I-75 traffic lanes will be open during peak hours.

    Night Work
    In order to maintain the construction schedule and to minimize the impact to the public, it is necessary for the contractor to also work at night. Lane closures, traffic shifts, and traffic paces will be used during different phases of the project.

    Lane Closure Hours
    9 p.m. to 6 a.m.

    Contact Person(s)

    Public & Media Contact
    John McShaffrey, APR
    Interstate Construction Office
    (813) 233-3837